Where the works stand in November 2026
| Part of the basilica | Status | Date |
|---|---|---|
| Tower of Jesus Christ | Finished at 172.5 m; cross 17 m tall and 13.5 m wide | 20 February 2026 |
| Blessing of the tower | Solemn Mass led by Pope Leo XIV | 10 June 2026 |
| Interior work | Continues through 2027 and 2028 | Expected 2028 |
| Glory Facade (main entrance) | Unfinished; progress held up by local opposition | No date given |
| Staircase to the entrance | Proposed; needs city approval and could require demolishing homes | Under discussion |
Dates and heights: Vatican News (21 February 2026), Catalan News, Time Out (June 2026), as of 12 November 2026.
The answer in one paragraph
Gaudí died in 1926 with the basilica only partly built. A hundred years later the central tower is complete, which is the milestone the builders aimed for. The words "finished" and "complete" still need care: the exterior of the central tower is done, the interior work will run until 2028 according to the reports, and the Glory Facade, begun in 2002, remains the open question because it depends on a street plan that residents and businesses contest.
Why has it taken since 1882?
- It relied on donations. The basilica has been paid for by private donations and, more recently, ticket sales, not by public or church money, so the speed depended on the money available (Wikipedia, 12 November 2026).
- Gaudí worked on it for decades. He took over in 1883 and was still at it when he died in 1926, when only about 15 to 25 percent was built. He reportedly said that his client was not in a hurry.
- The Civil War destroyed his models. In 1936 the crypt was set on fire and the workshop was broken into, partly destroying plans and models. Later architects rebuilt the designs from fragments, photographs and published plans.
- Work resumed slowly. Progress was slow in the 1950s. Computer-aided design and CNC milling sped things up later, and the project passed its midpoint in 2010.
- A pandemic stop. Construction paused in March 2020 for the first time since the Civil War.
- No building permit for 136 years. The permit was issued only in 2019, after the trustees paid the city 36 million euros.
What you will and will not see when you visit
You enter a working building. Cranes and scaffolding may still be around the towers and the Glory Facade, and some interior areas may be under work. The official audio guide, included in the 26-euro ticket, is available in the official app. For prices, the tower ticket, opening hours and the difference between the official site and resellers, read our Sagrada Familia tickets guide. If you want a hotel within walking distance, see where to stay near the Sagrada Familia.
Should you wait for the "finished" Sagrada Familia?
No. There is no single day on which the whole building will be declared finished, and the interior has been open to visitors for years. The tallest tower is complete, so the silhouette that will define the Barcelona skyline is now in place. Visit when it suits you, and book a timed ticket in advance: tickets are named, timed and sold online.
Figures to remember
- 1882: construction starts; 1883: Gaudí takes over; 1926: Gaudí dies.
- 20 February 2026: cross installed, Tower of Jesus Christ at 172.5 m.
- 10 June 2026: blessing of the tower, a hundred years after Gaudí's death.
- 2027 and 2028: interior work expected to continue.
- Glory Facade: begun in 2002, no end date.
These dates are current as of 12 November 2026 and can change as works progress.
Plan your visit
Book a morning slot to avoid the busiest hours and plan another stop afterwards: the Eixample district around the basilica is full of Modernista buildings within a short walk. The tower ticket adds 10 euros to the basilica ticket (36 euros against 26 euros, sagradafamilia.org, 8 November 2026).
FAQ
When will the Sagrada Familia be completely finished?
No single date is announced for the whole building. The central tower was completed in February 2026, interior work is expected to run through 2027 and 2028, and the Glory Facade has no completion date.
How tall is the Sagrada Familia now?
The Tower of Jesus Christ is 172.5 metres tall since the cross was completed on 20 February 2026 (Vatican News).
Is it worth visiting before it is finished?
Yes. The interior is open, the official ticket costs 26 euros, and the basilica has been open to visitors for years.
Barcelona Authority editorial team, 12 November 2026.